System structure with Gussasphalt on bridges
System structure
| Project | Replacement of the Röti Bridge
New construction pedestrian footpath T12 Rötistrasse Solothurn |
| Gussasphalt Surface Layer | MA 11 THP E spez. |
| Gussasphalt Tack Layer | MA 16 HP E spez. |
| Waterproofing bridge | PBD AE Pont GA 5 |
| Sealing | 2 layers epoxy resin |
| Area bridge | 4'000 sqm |
| Area footpath | 500 sqm |
| Surface chipping | Chipping 3/6, pre-coated with clear bitumen |
| Owner | Kanton Solothurn |
| Planner | Planergemeinschaft Quadras, c/o Bänziger Partner |
| Client | Implenia AG |
| Date of completion | April 2007 - September 2007 |
Project information
In 2003 the owner decided to tear down the old bridge and replace it by a new bridge with suspended footpath. Regarding the pavement structure, the owner opted for waterproofing bonded throughout to polymer bitumen sheeting and a two-layer, highly stable Gussasphalt pavement. The integrated track trenches were bedded on special elastic mats and backfilled with a specially adjusted Gussasphalt.
Execution
Execution of the waterproofing and paving work was conducted in several phases with full closure of the bridge new building. On account of the changing cross slopes, machine laying was conducted one lane at a time (length approx. 150m, width approx. 6.50m). The mastic asphalt in the track trench was installed by hand.
Structure
Surface chipping:
Chipping 3/6, pre-coated with clear bitumen
Topping:
37mm MA 11 THP E spez.
Binder course:
43mm MA 16 HP E spez.
Waterproofing:
5mm PBD AE Pont GA 5
Epoxy resin:
Priming and sealing
Concrete substructure